|
Argentine Mainline Fueling Expansion: The
existing mainline fueling facility was expanded from one fueling
platform to two fueling platforms. The design included the addition
of a new 800 GPM centrifugal diesel fuel pump, and the installation
of fueling cranes, and boom cabinets for lube oil and potable water.
Fueling platform design incorporated track pans, a secondary containment
system, and allowed for an expanded drainage capacity for the entire
fueling facility. The addition of the 800 GPM fuel pump brought
the total capacity of the two fueling platforms to 2,400 GPM, allowing
for simultaneous fueling of two, sets of six locomotive consists
at a fueling rate of 190 GPM per locomotive. The control system
was designed to match the existing system, using relay logic control,
but the design made provisions for converting the relay logic control
system to a PLC-based control system.
Argentine Mainline Diesel Fuel Transfer Line Replacement:
Approximately 6,000 lineal feet of double-wall, direct buried diesel
fuel piping was installed as a replacement to the existing single
wall steel piping. The double wall piping used a Schedule 40 steel
carrier pipe, with a fiberglass reinforced plastic, FRP, outer containment
pipe. The use of the FRP containment pipe eliminated the concerns
of corrosion and the need for cathodic protection of the piping.
Hanson-Wilson designed a system that connected an existing diesel
supply main, and supply diesel fuel to storage tanks located throughout
the facility. We determined the best routing of the pipes and coordinated
the routing with the existing utilities at the site. Also included
in the project was a Schedule 40 PVC pumped stormwater line, which
was installed parallel to the diesel fuel line. Pipe casings were
designed for all piping that crossed below tracks.
Argentine Valve Replacement: This project involved the
replacement of existing fuel system valves which had begun to leak.
Existing butterfly valves were replaced with new full port, Viton
seat ball valves. This project was unique because the facility remained
in operation throughout design and construction. The construction
documents detailed sequences of operation for each of the seven
locations.
|