|
|
 |
Direct to Locomotive Fueling Facility BNSF
Vancouver, Washington
 |
 This
project involved the design of a new DTL fueling facility for Burlington
Northern and Santa Fe Railway Company (BNSF) locomotives, along with a
variety of rail yard improvements; specifically, design of the DTL fueling
facility included installation of Lube Oil, Journal Oil, Sodium Borate
(Engine Radiator Water), and potable water systems. With each system,
special design consideration was given to the fact that the systems would
operate in cold weather and electrically heated boom cabinets were provided
to maintain the temperature of each system during periods of non-use.
In addition to the locomotive fueling and lubrication systems, a new sanding
tower was designed and installed. This sanding tower has the capability
of sanding two tracks simultaneously.
The unique aspect of the tower is the fact that the track centers are
wider than typically used in the standard facilities; therefore, the tower
height and dispensing arms had to be adapted to the project requirements.
The sanding tower footings were designed for Seismic Zone 3. A 40 horsepower
air compressor was relocated from the Portland, Oregon, yard for the sand
conveying system. New site lighting was provided at the DTL platform to
ensure a 24-hour operation. A new storm water lift station was provided
at the existing turntable, and two new sanitary sewer lift stations were
provided to replace older units that were nearing the end of their useful
lives.
A new grit chamber was provided to accommodate all of the rail yard wastewater.
The existing waste oil system was renovated. A new 25,000-gallon, double-wall
storage tank, along with a new 150 gpm positive placement pump was provided
to transfer waste oil, in double-contained piping, from the existing oil/water
separator to tanker cars.
Concerned with the safety of the BNSF personnel, a new fall protection
platform was provided at the waste oil loading station.
The new DTL platform required a great deal of rail yard track realignment
for which Hanson-Wilson Inc., provided all of the civil and site design.
Design was also provided for a variety of utility realignments including
a new 6" potable water line and relocation of 1500 feet of wastewater
piping.
A new maintenance support office building was provided. This office building
houses the fueling depot offices and locker/toilet rooms for the BNSF
personnel.
During the pre-design, our engineers worked closely with the City of Vancouver
in obtaining all of the required SEPA, erosion control, and building permits.
Following design, site observation trips were completed to track the project
progress and answer contractor questions.
|
 |