Central Park Boulevard Interchange with I-70 Design-Build - Denver, CO

This signature $30 million interchange design and construction project for the City and County of Denver serves as a gateway for visitors entering the city from Denver International Airport, as well as providing an important new interstate access within the city limits.

Minimizing impacts to the traveling public was identified as a key project goal which led to a combination of Accelerated Bridge Construction (ABC) techniques and Construction Management/General Contractor (CM/GC) delivery. This was the first bridge design and construction utilizing this method for CDOT.

Braided ramp networks on both sides of I-70 provides direct access to and from both I-70 and I-270 with the Stapleton community, and local shopping.

 

Fast Facts:

  • The project utilized an integrated design and construction process allowing initial construction activities to begin in May of 2010
  • The majority of the design was completed by the summer of 2010 allowing the project stay on track and become fully operational by November of 2011
  • The $30 million interchange design and construction was primarily funded and managed by the City & County of Denver, in partnership with the Colorado Department of Highways
  • The project included $12 million of American Recovery and Reinvestment funds, requiring an expeditious process in both design and construction
  • The project was in an environmentally sensitive area that has been preserved through an Environmental Compliance Plan executed by Wilson & Company
Client 
City and County of Denver
Services Provided 

As the lead designer, teamed with SEMA Construction, Inc. we provided the following services:

  • Design of three major bridge structures
  • Roadway design
  • Drainage design
  • Traffic
  • Maintenance of traffic design
  • Overall design project management
  • Quality Management leadership